NHI: Digging the potential of maintenance to create benefits for enterprise

Published:2022-10-07

8X20M Moveable-7-axis (5 interlockable) NC Heavy-duty Two-column Mill, commonly known as "seven axis five linkage", is a high-precision machining equipment of Northern Heavy Industries Group Co., Ltd. (hereinafter referred to as "NHI"). In April this year, the equipment failed - the universal milling head could not be used, which seriously affected the processing nodes of relevant key products.

Universal milling head is a high-precision accessory of the equipment. NHI has no experience in repairing the same type of precision equipment before. Through external consultation, only one enterprise in Shenyang can provide maintenance services, but the maintenance cost may reach 500,000.00 yuan, which cannot guarantee the maintenance effect.

In order to save maintenance costs, reduce maintenance risks, and at the same time train the maintenance team and improve skills, NHI organized and coordinated the Large Component Manufacturing Branch, Design and Research Institute, Production Command Center, and Automation Branch to jointly establish a milling head maintenance working group and carry out self repair work.

In the face of sophisticated and complex imported equipment, NHI dispatched professional backbones from all aspects to fully cooperate in the emergency repair work, overcome the difficulties such as the lack of equipment drawings and incomplete data, and members of the emergency repair team searched for information on the site, checked the lines, found faults item by item, accurately located the fault points, and jointly studied the replacement of damaged parts. Through joint efforts, they completed the milling head disassembly, seal replacement, pin and other electrical components maintenance, reinstallation, electrical debugging and other related work, and successfully passed the test run, saving the maintenance cost of 202,300.00 yuan for the enterprise.

In addition, with the joint efforts of Production Command Center, Structural Parts Branch and Design and Research Institute, the self repair work of the pretreatment line equipment in Structural Parts Branch of NHI was successfully completed, which not only revitalized important equipment, but also saved more than 360,000.00 yuan in maintenance costs for the enterprise. At present, the equipment runs smoothly and achieves the expected goal.

The relevant person in charge of NHI said that the enterprise had found a "new way" in self-reliance, cost reduction and efficiency increase by digging deep into maintenance potential and cultivating maintenance teams.


主站蜘蛛池模板: 国产**一级毛片视频直播| 九一在线完整视频免费观看| 99视频在线看观免费| 福利视频第一区| 小小的日本电影在线观看免费版| 放荡的女老板bd中文字幕| 国产成人无码区免费A∨视频网站 国产成人无码区免费内射一片色欲 | 最新亚洲人成无码网站| 国产的一级毛片最新在线直播| 亚洲另类春色国产精品| 亚洲综合伊人制服丝袜美腿| 欧美bbbbxxxx| 国产成人综合野草| 久久午夜无码鲁丝片秋霞| 青青草97国产精品免费观看| 日本精高清区一| 国产精品青青青高清在线观看 | 国产麻豆精品入口在线观看| 亚洲精品免费在线视频| 久久久久久久99精品国产片| 一级有奶水毛片免费看| 极品美女a∨片在线看| 国产婷婷成人久久av免费高清| 久久成人国产精品| 老师好紧开裆蕾丝内裤小说| 小雪把双腿打开给老杨看免费阅读| 免费a级毛片在线播放| 999无色码中文字幕| 欧美国产日韩a在线视频| 国产成人天天5g影院| 久久久久久久伊人电影| 精品国产一区二区三区2021| 大ji巴c死你h| 亚洲人成人一区二区三区| 黄大色黄美女精品大毛片| 欧美一区欧美二区| 国产剧情在线视频| 中国一级特黄的片子免费 | 交换美妇94系列部分| 18禁裸体动漫美女无遮挡网站| 日韩高清第一页|